AUSTRALIAN NATIONAL UNIVERSITY

 

System Design Note 12.00

 

Created: 12 April 2000

Last modified: 0 XXX 0000

 

---

 

NIFS CODR MANAGEMENT PLAN

 

Jan van Harmelen

 

Research School of Astronomy and Astrophysics

Institute of Advanced Studies

Australian National University

 

Revision History

 

Revision No.

Author &

Date

Approval &

Date

Description

Revision 1

Jan van Harmelen

12 April 2000

Peter J. McGregor

12 April 2000

Original document.

 

 

 

 

 

 

Contents

 

1 Purpose. 1

2 Applicable Documents. 2

3 Introduction. 2

4 Section Headings. 2

Appendix A: List of Figures. 2

 

 

1 Purpose

 

This document presents the management plan for the further design, construction, assembly, testing, and commissioning of the Gemini Near-infrared-Integral-Field Spectrograph (NIFS).

 

2 Applicable Documents

 

Document ID

Source

Title

 

 

 

 

 

3 Introduction

 

This document contains the management information for the Gemini Near-infrared Integral-Field Spectrograph (NIFS). This includes costing and planning information as well as information about the Research School of Astronomy and Astrophysics (RSAA) in the Institute of Advanced Studies (IAS) of the Australian National University (ANU) and its staff involved in the project.

 

RSAA have produced a conceptual design for NIFS and this management plan proposes cost and time estimates for building this instrument.

 

All costs are quoted in United States dollars, exclusive of the Goods and Services Tax to be introduced on 1 July 2000 which is expected not to affect the cost of NIFS (refer to § 10.6).

 

The NIFS development is to be fast-tracked to ship the instrument to the Gemini base facility in Hawaii in June 2002 for deployment on the Gemini North telescope later that year. To accomplish this with as little risk as possible, the cryostat, the OIWFS, and large parts of the control system will be copied from NIRI and implemented by its developers at the Institute for Astronomy (IfA) of the University of Hawaii (UH). Significant gains on the timeline can be realised by not following the usual pattern of Preliminary Design, Critical Design, and then Manufacture phases. Instead, it is proposed that manufacture of the cryostat and the OIWFS start immediately, and the spectrograph Preliminary Design Review be dispensed with.

 

4 Work Breakdown Structure (WBS)

 

The WBS chart, Figure 1, shows the first two levels of the Work Breakdown Structure for the project. The full breakdown is shown in Appendix §13.2.

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Figure 1: NIFS WBS Chart


4.1 NIFS Critical Design Study

 

During the NIFS Critical Design Study, the optical design is to be finalised, the mechanical design is to be progressed through to the production of manufacturing drawings. The detector system is to be designed in full detail and wiring for a test cryostat is to be designed and manufactured. The overall software system design is to be completed together with the Components Controller and Instrument Sequencer software.

 

Any optical design issues still outstanding at the Conceptual Design Review need to be addressed. These include scattering, ghosting, tolerancing, and alignment needs and accuracy. The manufacturing details of all optical components need to be specified and decisions need to be made on which items will be fabricated in-house. The blanks for in-house fabrication have to be ordered and contracts let for the supply of gratings and filters. It would be advantageous to start in-house fabrication early and possibly also let the external optics manufacturing contracts.

 

In the area of mechanical design, full assembly drawings of the spectrograph are to be produced. These, together with information from NIRI will be used for flexure and thermal analysis. Detailed manufacturing drawings of all lens and mirror mounts, baffles, shields, and mechanisms have to be produced. We are planning a short and intensive fabrication phase, and it would be advantageous to start fabrication of some components early to reduce the risk of fabrication delays due to unexpected variations in workshop staff availability and the impact of other workloads. We would identify components for early fabrication taking into account the least impact of possible spectrograph design changes in the latter part of the Critical Design Study or at the CDR.

 

The detector and detector controller are long lead-time items which should be ordered as soon as possible. The operation of the controller will have to be fully verified upon delivery. The wiring from the controller to the detector has to be fully detailed with circuit diagrams showing all signals, connectors and printed circuit boards. Some issues identified during the conceptual design, such as choice of materials for printed circuit substrates and flexible circuits need to be addressed. The test cryostat wiring has to be designed and manufactured. The DSP code for the detector controller needs to be designed.

 

The overall software system design should be finalised and the NIFS Component Controller software should be ready for testing. The Detector Controller software design should be completed and coding should be under way for the detector engineering software.

 

Other items to be delivered are final ICDs, tables of contents for all manuals, a draft spares list, the pre-shipment acceptance test plan and the verification and commissioning plan.

 

4.2 NIRI Duplication

 

It is proposed that RSAA subcontract the manufacture, assembly, and test of the "NIRI duplication" to the Institute for Astronomy of the University of Hawaii. Except for a few relatively minor changes, the following NIRI items will be duplicated: carrier frame, ISS interface plate, cryostat, cooling system, OIWFS optics and mechanics, OIWFS detector and controller, electrical control system, and temperature control system.  The full assembly will be tested before delivery to RSAA. On delivery, it will be re-tested to check that no transport damage has occurred.

 

4.3 Spectrograph Manufacturing Phase

 

Optical manufacture, both in-house and subcontracted, will be continued following the Critical Design Review. Contracts will be let for the manufacture of the IFU and of those optical elements which were not ordered earlier during the design phase.

 

All mechanical parts (lens and mirror mounts, baffles, shields and mechanisms) will be fabricated. Trial assembly of the spectrograph on a copy of the cold work surface plate incorporated in the NIRI duplication will start as soon as there are mechanisms and other items ready for assembly. When complete, optical alignment procedures can be tested and the NIRI control system can be used to check mechanism operation under full software control.

 

Mechanical modifications have to be designed and implemented to transform an existing 8 inch IR Labs dewar  into a test cryostat for the NIFS detector. Two sets of detector circuit boards and wiring will have to be designed and constructed. The first to allow independent testing of all four detector quadrants and the second for normal operation. The detector engineering array will arrive during the manufacturing phase. It will be tested in the test cryostat with the detector engineering software.

 

The software effort will be structured so that sufficient engineering software will be available for the tests with the engineering detector in the test cryostat and for the mechanism tests in the trial mechanical assembly.

 

The user and maintenance manuals will be prepared.

 

4.4 NIFS Assembly and Testing

 

Following rectification of any problems found during the spectrograph trial assembly on the dummy cold work surface plate, the spectrograph can be integrated into the cryostat. As the cryostat and OIWFS system have already been fully tested and the spectrograph has been tested warm, the optics and engineering detector can be installed on the first cooldown cycle. The objectives of the first cooldown are to determine the thermal characteristics of the detector mounting and spectrograph, to verify cold operation of the mechanisms, to verify detector operation, to go through the first phase of measuring optical alignment, and to do mechanical stability tests. After rectification of problems encountered and corrective alignment of the optics, the second cooldown can start. The optical alignment will be checked and all tests repeated. After installation of the science detector, a third cooldown should permit full system tests to be performed. A final period for corrective actions leads to the fourth cooldown cycle for pre-delivery acceptance tests. At the end of this, NIFS is packed and transported to the Gemini base facility in Hawaii. This success-oriented scenario is somewhat optimistic and allows only for limited problem rectification times between cooldowns, and does not allow for optical alignment to be iterative. The Assembly and Testing work package therefore contains a contingency for two extra cooldowns.

 

4.5 NIFS Commissioning

 

After transportation to the Gemini base facility in Hawaii key acceptance tests should be repeated to check for transport damage. NIFS can now be transported to the summit and connected to the various interfaces to integrate it with the observatory systems. It can then be prepared for commissioning on the telescope.

 

Training for Gemini operations and maintenance staff will be provided, the manuals will be updated and the record documents will be finalised.

 

5 Schedule

 

An overview of the schedule for the NIFS development is depicted in Figure 2. A fully detailed Gantt chart appears in Appendix §13.1.

 

Figure 2: NIFS Schedule

 

 

5.1 Milestones

 

The proposed milestones for this project are shown in Table 1 below.

 

Table 1: Milestones

CDS start

1 April 2000

Detector Ordered

2 May 2000

Detector Bare MUX delivered

4 September 2000

Delivery of CDR documentation

24 November 2000

CDR

8 December 2000

NIRI Duplicate delivery

17 May 2001

Engineering Array delivery

5 April 2001

Start of first NIFS cooldown

5 October 2001

Science detector delivery

5 November 2001

Ship NIFS to Hawaii

20 June 2002

First commissioning night

August 2002

Project closeout

Nov 2002

 

 

5.2 Spectrograph Critical Design Study

 

The Critical Design Study will terminate with the Critical Design Review. The date of the review is driven by the work to be done and the availability of suitably qualified and experienced staff to do it. Mechanical design is on the critical path. Completion of the design phase is planned for December 2000.

 

5.3 NIRI Duplication

 

The NIRI duplication work needs to be started soon and delivery of the tested system is planned before the end of the spectrograph manufacturing phase so that the spectrograph mechanisms can be tested warm with their actual control system and software before integration of the spectrograph into the vacuum jacket. The main fabrication effort should take place in mid 2000, with assembly and testing to commence later in the year. Delivery should be in early 2001.

 

5.4 Spectrograph Manufacturing Phase

 

The manufacture of mechanical parts for the spectrograph will be the limiting factor on keeping this phase to minimum length, as long as the optical manufacture can be started early and much of it can be subcontracted. It is envisaged to have three instrument makers working full time on NIFS for this period. This means that RSAA will have to employ at least one, possibly two, extra workshop staff.

 

A test cryostat will be built by modifying an existing dewar. The test cryostat should be ready around the time of delivery of the engineering detector. After delivery of the science detector, the detector engineer’s time is to be divided between the testing of the engineering detector in the NIFS cryostat and the science detector characterisation in the test dewar. To do this, two SDSU controllers will be needed. The RSAA detector lab controller will be used, for which at least one IR analog card will need to be purchased.

 

Software production for test dewar operation is expected to be on the critical path to the testing of the engineering array in the test cryostat.

 

5.5 NIFS Integration and Test

 

The installation of the spectrograph in the cryostat and three cooldown, test, warmup, and problem fixing cycles are expected to take up to seven months. As contingencies, two more cooldowns are budgeted for, but not scheduled. These would add two to three months to the schedule.

 

A final fourth cooldown cycle is planned to accommodate pre-delivery acceptance tests. On successful conclusion of these tests, NIFS will be warmed up, packed, and transported to the Gemini base facility in Hawaii.

 

5.6 NIFS Commissioning

 

Commissioning will start by repeating the acceptance tests to check for transport damage. The instrument will then be transported to the summit and integrated into the observatory systems. Two months will elapse from arrival in Hawaii to being ready for the first night on the telescope. NIFS will be tested, commissioned, and verified under varying observing conditions during the commissioning nights, and any problems will be rectified. Gemini staff will be trained in the operation and maintenance of the instrument. The time taken will depend on the commissioning time made available and on the nature and seriousness of any problems encountered.

 

6 Cost

 

As shown in Table 2, the total cost of NIFS, excluding the detector, is US$2,996,319. The cost of the HAWAII-2 HgCdTe/PACE detector is US$350,000.

 

Table 2: NIFS Cost Breakdown by Activity

 

Description

hrs

US$

 US$

Labour

Project Scientist

1383

 $                -

 

 

Project General

2210

 $      77,350

 

 

System Engineering

2390

 $      83,650

 

 

Mechanical Design

1830

 $      64,050

 

 

Mechanical Manufacture

3200

 $    112,000

 

 

Optical Design

710

 $      24,850

 

 

Optical Manufacture

530

 $      18,550

 

 

Detector System Design & Manufacture

3020

 $    105,700

 

 

Control System Design & Manufacture

344

 $      12,040

 

 

Software Development

3270

 $    114,450

 

 

Assembly & Testing

2240

 $      78,400

 

 

Commissioning

570

 $      19,950

 

subtotal

 

21697

 

 $      710,990

 

 

 

 

 

Major Items

NIRI Duplication

 

 

 $   1,750,000

 

 

 

 

 

Hardware Costs

 

 

 

 

Mechanical

 

 $      21,930

 

 

Optical

 

 $    111,300

 

 

Detector System

 

 $      33,275

 

 

Control System

 

 $        7,918

 

 

Computing

 

 $      57,306

 

 

Thermal Enclosures

 

 $      14,000

 

 

Subcontractors (design)

 

 $      11,385

 

 

Consumables

 

 $        9,000

 

subtotal

 

 

 

 $      266,114

 

 

 

 

 

Other Costs

Project Management (incl. CDR)

 

 $      21,000

 

 

Travel (excl. commissioning)

 

 $      17,500

 

 

Transportation

 

 $      72,000

 

 

Extra Cooldowns

 

 $      35,000

 

 

Support Equipment

 

 $      43,715

 

 

Contingencies

 

 $      60,000

 

 

Commissioning Travel

 

 $      20,000

 

subtotal

 

 

 

 $      269,215

total

 

 

 

 $   2,996,319

 

 

6.1 Labour

 

Table 3 shows that the labour required for the spectrograph design and construction, and for the instrument assembly, testing and commissioning is 21697 hours. At the RSAA labour rate of US$35 per hour, and taking into account that time worked by the Project Scientist is not chargeable, this comes to $ 710990. For a full breakdown of the labour required refer to the detailed Gantt chart in Appendix §13.1. The labour estimates are based on RSAA's previous experience building instruments.

 

Table 3: NIFS Cost Breakdown by Development Phase

Phase

PS hrs

Paid hrs

 Labour

 Fixed Cost

 Total Cost

Critical Design Study

627

6303

 $     220,605

 $     119,026

 $      339,631

Cryostat and OIWFS Duplication

140

140

 $         4,900

 $  1,785,500

 $   1,790,400

Spectrograph Construction

70

9419

 $     329,665

 $     201,188

 $      530,853

NIFS Assembly and Testing

308

3688

 $     129,080

 $     118,615

 $      247,695

Extra Cooldowns

 

 

 

 $       35,000

 $        35,000

Commissioning

238

764

 $       26,740

 $       26,000

 $        52,740

total

1383

20314

$      710990

$    2285329

 $   2,996,319

 

 

6.2 Capital

 

A large part of the total NIFS project cost is for the duplication of NIRI (US$1.75M). The cost of all further items to be purchased for the construction comes to US$ 535329. The uncertainties associated with the capital cost estimates are identified in Table 5.

 

The line-item "Consumables" in Table 2 refers to minor parts and materials such as fasteners, common cables, and other small items which will be needed but are not yet identified.

 

The line-items "Computing" and “Thermal Enclosures" are Gemini supplied items for which the cost has to be included in the NIFS budget. The "Computing" costs are itemised in Table 6: Gemini Supplied Items.

 

6.3 Travel and Miscellaneous

 

The travel budget allows for two visits of project staff to Hawaii related to the NIRI duplication and three more trips, possibly to other destinations, as the need arises.

 

Travel for the Commissioning phase has been included as fixed cost in one of the commissioning tasks. The allocation is for four people travelling to Hawaii, staying there for 3.5 weeks on average.

 

The cost of transportation of NIFS to Hawaii is covered under the heading "Shipping". Transportation of the NIRI duplicate to Australia is included in the "NIRI Duplication" cost.

 

The Project Management tasks have fixed cost entries for the cost of photocopying, printing, telephone, etc. and to cover unforeseen expenditure, which does not fit in any other category.

 

6.4 Contingency

 

Several levels of contingency are to be considered for the project. At the highest level Gemini will maintain a contingency for the cost of change orders and major problems such as cost variations of the NIRI duplication.

 

The NIFS project plan contains a contingency for the cost of extra cooldowns, for some as yet unspecified travel and the project management tasks have fixed cost entries for the cost of photocopying, printing, telephone, etc. and to cover unforeseen expenditure which does not fit in any other category. Two more “Contingency” items are listed, one for the spectrograph construction phase and one for the assembly and test phase. They are intended to cover items missed in costing, underestimated, fabrication mishaps, printed circuit redesign, equipment failures, etc. The total of these contingency items is $60000, a very modest 4.8% of the spectrograph cost (excluding the NIRI duplication).

 

Some individual tasks, which have a high risk of taking longer than planned in this success-oriented schedule, have been allocated extra effort in the plan.

 

6.5 Cost Profile per Quarter

 

The cost profile of the NIFS project is shown in Figure 3. This information is only indicative of the cashflow for the project. It was generated by Microsoft Project on the assumptions that labour costs are accrued as work is executed, and fixed costs become payable at the start of their associated tasks, with the exception of the NIRI duplication where pro-rata cost accrual over the whole construction period has been used.

 

During the first half of the project, in the design and construction phases, 87% of the cost is accrued.

Figure 3: NIFS Cost per Quarter

7 Procurement List

 

Listed in Table 5 are all items to be purchased for the NIFS development as they have been identified during the conceptual design study. The accuracy of the costs in the table is indicated by the “code” as defined in Table 4.

 

Table 4: Cost Codes

Code

Definition

Costing Method

W

Estimate ±40%

Extrapolation from past experience

E

Estimate ±20%

From recent relevant experience

Q

Quoted cost

From manufacturer's quotation

 

Table 5: Items to be Purchased

Item

Code

Est. Cost

Vendor

Order Date

Notes

  NIRI Duplication

Q

 $  1,750,000

UH

Apr  2000

 

  Spectrograph

 

 

 

 

 

    Optics

 

 

 

 

 

      Pick-Off Mirror

E

 $         3,000

POE

Nov 2000

diamond machined

      Focal Ratio Converter Mirror

E

 $         3,100

POE

Nov 2000

diamond machined

      Cold Stop Mirror

E

 $         2,000

POE

Nov 2000

diamond machined

      Fold 1 Mirror

E

 $         1,900

POE

Nov 2000

diamond machined

      Fold 2 Mirror

E

 $         1,800

POE

Nov 2000

diamond machined

      Tri-Fold Mirror

E

 $         6,000

POE

Nov 2000

diamond machined

      Image Slicer

E

 $         4,000

POE

Nov 2000

diamond machined

      Pupil Mirror Array

E

 $       13,000

POE

Nov 2000

diamond machined

      Field Mirror Array

E

 $       13,000

POE

Nov 2000

diamond machined

      Collimator Mirror (blank)

E

 $         1,400

 

Jul 2000

Silica

      Collimator Corrector (blank)

E

 $         1,300

 

Aug 2000

CaF2

      Camera Lens 1 (blank)

E

 $         1,800

 

Aug 2000

CaF2

      Camera Lens 2 (blank)

E

 $         1,700

 

Aug 2000

Silica

      Camera Lens 3

E

 $         6,000

JNS

Oct 2000

ZnSe: from Janos

      Camera Lens 4 (blank)

E

 $         1,800

 

Aug 2000

CaF2

      Camera Lens 5 (blank)

E

 $         1,600

 

Aug 2000

Silica

      Order Blocking Filters

 

 

 

 

 

        J and K

E

 $         2,936

GEM

available

from Filter Consortium

        TBA

E

 $       32,064

 

 

2 sets of 4 @ $4000 ea

      Gratings

 

 

 

 

 

        TBA

E

 $       10,400

RGL

 

8 @ $1300

      Ronchi Grating and Occult. Masks

 

 

 

 

 

        Materials and Coating

W

 $         2,500

 

Aug 2000

 

    Mechanical (materials incl. motors)

 

 

 

 

 

      Set-Up Plate

E

 $            800

 

Sep 2000

1000x800x40,100 features

      Spectrograph Enclosure

E

 $         4,000

 

Dec 2000

Casting, 50 machined features

      Disperser Enclosure

E

 $            600

 

Dec 2000

Casting, 30 machined features

      Small Enclosure components

E

 $              60

 

Jan 2001

40 small pieces with repetition

      Radiation Shield Oddments

E

 $              60

 

Feb 2001

6 small pieces

      Entrance Baffle

E

 $                 -

 

Feb 2001

180 x 180 x 250, fabrication

      Pick-Off Probe

E

 $              60

 

Sep 2000

8 pieces plus optics

      Feed Turret

E

 $         2,500

 

Aug 2000

69 pcs, motor, masks, mirrors

      Filter and Folder Unit

E

 $         2,500

 

Nov 2000

66 pieces, motor

      Field Slicer

E

 $         1,000

 

Sep 2000

46 pieces, plate rolling

      Mirror Array and Folder Unit

E

 $              60

 

Dec 2000

10 pieces

      Collimator Reflector

E

 $              60

 

Jan 2001

8 pieces

      Collimator Corrector

E

 $              60

 

Jan 2001

6 pieces

      Disperser

E

 $         3,000

 

Aug 2000

48 pcs, motor, enc., latching

      Camera

E

 $              60

 

Oct 2000

22 mechanical pieces

      Detector Mount

E

 $              60

 

Nov 2000

35 pieces

      Detector Controller Mount

E

 $                 -

 

Feb 2001

Integrated connector

      Handling Equipment

W

 $         2,000

 

Mar 2001

 

      Alignment Aids

W

 $            400

 

Mar 2001

 

      Bearings etc. for Mechanisms

 

 

 

 

 

        Sintered Components

E

 $            250

 

Dec 2000

 

        Bearings

E

 $         1,000

 

Dec 2000

 

        Indium Foil & Incidentals

W

 $         1,000

 

Dec 2000

 

      Test Cryostat Mods (materials and parts)

 

 

 

 

        TBA

W

 $         1,500

 

 

 

      Components Surface Treatment

 

 

 

 

 

        Paint

W

 $            900

 

Apr 2001

 

    Control System

 

 

 

 

 

      Thermal Cabinets

Q

 $       14,000

GEM

available

ready for delivery

      Mechanism control

 

 

 

 

 

        Hall Effect Sensors

E

 $            550

FWB

Oct 2000

 

        Magnets

W

 $              50

 

Oct 2000

 

        connectors and wiring

W

 $            300

 

Nov 2000

 

      Temperature Control

 

 

 

 

 

        Temperature Controller

Q

 $         5,120

LCI

Jul 2000

 

        Rack Mount

Q

 $            118

LCI

Jul 2000

 

        Calibrated Sensors

Q

 $         1,220

LCI

Jul 2000

 

        Heater Cartridges

W

 $            170

LCI

Jul 2000

 

        Heater Resistor

E

 $              30

 

Jul 2000

 

        Diode Sensors

W

 $              60

 

Jul 2000

 

        connectors and wiring

W

 $            300

 

Jul 2000

 

    Detector System

 

 

 

 

 

      Detector Controller

 

 

 

 

 

        Fiber Optic Timing Board

Q

 $         2,500

LCH

April 2000

 

        Dual Channel IR Video Board (2)

Q

 $       10,000

LCH

April 2000

 

        Clock Driver Board

Q

 $         2,500

LCH

April 2000

 

        VME Interface Board

Q

 $         3,750

LCH

April 2000

 

        Controller Housing and 6-slot Backplane

Q

 $         2,500

LCH

April 2000

 

        Power Supply for 6-slot

Q

 $         1,250

LCH

April 2000

 

        100' Fibre Optic Cable (2)

Q

 $            300

LCH

April 2000

 

        Set of Electronics Cables

Q

 $         1,000

LCH

April 2000

 

        Set of Shorting Plugs

Q

 $            375

LCH

April 2000

 

      Detector Wiring

 

 

 

 

 

        Shorting Connectors

W

 $            400

 

April 2000

 

        Cryostat Internal Wiring

 

 

 

 

 

          Wiring Tests -rectification

W

 $            100

 

 

 

          Detector Mounting PCB

 

 

 

 

 

            Detector Sockets

E

 $            600

 

April 2000

 

            Discrete Components

E

 $            160

 

May 2000

 

            Flex Circuit Mating Connectors

E

 $            195