AUSTRALIAN NATIONAL UNIVERSITY

 

System Design Note 4.16

 

Created: 24 April 2002

Last modified: 8 May 2002

 

---

 

INTEGRATION AND TEST PLAN

 

Peter J. McGregor

 

Research School of Astronomy and Astrophysics

Institute of Advanced Studies

Australian National University

 

Revision History

 

Revision No.

Author &

Date

Approval &

Date

Description

Revision 1

Peter J. McGregor

9 January 2002

Jan van Harmelen

10 January 2002

Original document.

Revision 2

Peter J. McGregor

6 May 2002

Jan van Harmelen

8 May 2002

Revised after Gemini comment.

 

 

Contents

 

1 Purpose. 2

2 Applicable Documents. 2

3 Introduction. 2

4 Schedule of Tasks. 2

5 Equipment Needed. 2

5.1 Lifting Cranes and Cross Beam.. 2

5.2 Vacuum Pump and Hoses. 2

5.3 Coolant, Dry Air, and Helium Supplies. 2

5.4 Computer Systems. 6

5.5 Transport to Summit 6

6 Staff Movements. 6

7 Preliminary Cost 7

 

 

1 Purpose

 

This document describes the steps required to take the Gemini Near-infrared Integral Field Spectrograph (NIFS) from the completion of acceptance tests at RSAA to first light on the Gemini North telescope.

 

2 Applicable Documents

 

Document ID

Source

Title

SDN0004.09

RSAA

NIFS Acceptance Test Plan

 

 

 

 

 

3 Introduction

 

The Gemini Near-infrared Integral Field Spectrograph will undergo acceptance tests at RSAA. These are described in SDN0004.09. This Integration and Test Plan describes the steps that are required following these acceptance tests to pack NIFS, ship it to Hawaii, perform integration and tests at the Hilo Base Facility, transport it to the Gemini North telescope, and prepare it for first light.

 

4 Schedule of Tasks

 

The schedule of tasks to be performed is shown in Figure 1, Figure 2, Figure 3, and Figure 4.

 

5 Equipment Needed

 

5.1 Lifting Cranes and Cross Beam

 

An overhead gantry fitted with two electric cranes is needed both at the Hilo Base Facility (HBF) and at the summit to lift the integration frame and the completely assembled instrument. These are standard Gemini items that are detailed in ICD 1.5.3/1.9.

 

A total of four handling carts and trolleys will be supplied by RSAA with NIFS. These trolleys will support the two thermal enclosures, the cryostat, and the integration frame during assembly. The integration frame trolley is designed to carry the complete 2 ton instrument.

 

5.2 Vacuum Pump and Hoses

 

The Gemini vacuum pump used to pump NIRI is needed to pump NIFS at the HBF and at the summit. An ISO-40KF fitting is required to connect the pump to the NIFS vacuum lock fitting. This is similar to that required for NIRI.

 

5.3 Coolant, Dry Air, and Helium Supplies

 

Standard coolant, dry air, and compressed helium supply and return connections are required at HBF and at the summit.

 

Figure 1: Integration and Test Schedule

Figure 2: Integration and Test Schedule (cont'd)

Figure 3: Integration and Test Schedule (cont'd)

Figure 4: Integration and Test Schedule (cont'd)

 

 

5.4 Computer Systems

 

A stand-alone workstation will be provided by RSAA to control the instrument initially.

 

Access to instrumentation computers, disk space, and workstations are required to install NIFS software and operate instrument at HBF and summit.

 

5.5 Transport to Summit

 

After completion of the testing phase at the HBF, the NIFS subsystems will be dismantled, packed, and transported to the summit on the Gemini truck. This may require several journeys. This time period could be shortened if a suitable 3.5t enclosed truck were available and able to make the journey to the summit.

 

Each of the NIFS instrument components will fit within the Gemini dome elevator.

 

6 Staff Movements

 

Table 1listed the scheduled staff movements.

Table 1: Staff Movements During Integration and Test

Person

Arrive

Depart

Days in Hilo

Days at Summit

Days at Gemini

Days in Transit

Total Days

Conroy

31-JUL-03

12-AUG-03

13

0

13

3

16

 

29-AUG-03

09-SEP-03

6

6

12

3

15

 

24-SEP-03

26-SEP-03

0

3

3

3

6

Dawson

29-AUG-03

09-SEP-03

6

6

12

3

15

Downing

12-AUG-03

21-AUG-03

10

0

10

3

13

 

19-SEP-03

24-SEP-03

0

6

6

3

9

 

04-OCT-03

20-OCT-03

0

17

17

3

20

Hart

31-JUL-03

04-AUG-03

5

0

5

3

8

 

14-OCT-03

20-OCT-03

0

7

7

3

10

Jarnyk

01-AUG-03

11-AUG-03

11

0

11

3

14

 

21-AUG-03

29-AUG-03

9

0

9

3

12

 

17-SEP-03

26-SEP-03

0

10

10

3

13

McGregor

12-AUG-03

26-AUG-03

15

0

15

3

18

 

04-OCT-03

20-OCT-03

0

17

17

3

20

van Harmelen

31-JUL-03

11-AUG-03

12

0

12

3

15

 

26-AUG-03

05-SEP-03

9

2

11

3

14

 

17-SEP-03

26-SEP-03

0

10

10

3

13

Young

01-AUG-03

11-AUG-03

11

0

11

3

14

 

21-AUG-03

02-SEP-03

13

0

13

3

16

 

04-OCT-03

20-OCT-03

0

17

17

3

20

Total

 

 

120

101

221

60

281

 

 

7 Preliminary Cost

 

The following gives a very preliminary costing of the Integration and Test phase. It is expected that this costing will evolve as the task time estimates are firmed up and more accurate airfare and accommodation costs are obtained.

 

Staff salaries is costed at $US280/day assuming a $US35/hr and 8 hr/day. Accommodation and meals are costed at $US150/day in Hilo and $US100/day at the summit. Airfares are costed at $US1000/trip. The cost of one hire car for the duration of the plan is also included. Contingencies are costed on the basis of two 7 day trips (plus 3 days transit) to Hawaii during the Hilo phase and two 7 day trips during the summit phase. The preliminary total cost is $US155,080 as itemized in Table 2.

 

Table 2: Integration and Test Plan Costs

Item

Units

Rate

Cost

Base plan:

 

 

 

Salaries

281 days

$US280/day

78,680

Accommodation

 

 

 

- Hilo

120 days

$US150/day

18,000

- Summit

101 days

$US100/day

10,100

Airfares

20 trips

$US1000/trip

20,000

Hire car

82 days

$US100/day

8,200

Base plan total

 

 

134,980

 

 

 

 

Contingencies:

 

 

 

Salaries

40 days

$US280/day

11,200

Accommodation

 

 

 

- Hilo

14 days

$US150/day

2,100

- Summit

14 days

$US100/day

1,400

Airfares

4 trips

$US1000/trip

4,000

Hire car

14 days

$US100/day

1,400

Contingencies total

 

 

20,100

 

 

 

 

TOTAL

 

 

155,080