|
|
AUSTRALIAN NATIONAL UNIVERSITY Monthly
Report 8 Created: 10 October 2000 Last modified: 16 October 2000 |
MONTHLY REPORT FOR SEPTEMBER 2000
Jan van Harmelen
Research
School of Astronomy and Astrophysics
Institute
of Advanced Studies
Australian
National University
Revision
History
|
Revision No. |
Author & Date |
Approval & Date |
Description |
|
Revision 1 |
Jan
van Harmelen 10 October 2000 |
Peter McGregor 16 October 2000 |
Original document. |
|
|
|
|
|
Contents
There
is no progress to report on NIFS science.
Although the NIFS
contract has not been fully executed at this point in time, RSAA submits this
monthly report on NIFS activities, covering the period from 4 to 29 September
2000.
The period of
uncertainty waiting for NSF approval of the NIFS contract still continues. RSAA
continued design and fabrication work, but has not placed any further orders
for equipment and materials. This may cause delays in the purchase and delivery
of long leadtime items, eventually impacting on project completion. It is also
holding up negotiations on a contract for cooperation with UH. RSAA and Gemini
are exploring how the purchase of long leadtime and/or expensive items can be
organised without RSAA assuming the financial risk associated.
Progress on CC and IS
software development, control system design and procurement, and cryostat and
OIWFS duplication is being hampered by the non-availability of NIRI as-built
documentation.
The search for
competent design and workshop staff continues. Leigh Pfitzner, a designer from
Auspace Ltd. Continues to work at RSAA. to overcome the skills shortage. Other
avenues to fill these positions are being explored.
The three temporary
(18 months) machinist positions in the workshop to fabricate parts for the NIRI
duplication and later for the spectrograph have all been filled.
The advertisement for
an electronics technical officer has brought a disappointing response. An
employment agency has been engaged to find other suitable candidates. This is a
continuing position vacated earlier in the year, which needs to be filled
together with a temporary position to allow the fabrication of the NIFS control
system.
Our review of the
optical design of the spectrograph was completed. However, the sheet metal
material procured for the fabrication of the field slicer is thinner than
specified. Unless material of the correct thickness can be obtained, the
optical design will have to be re-optimised for the smaller slicer size.
The assembly design of
the grating mechanism took longer than expected and is now nearing completion.
The first pass design of all other spectrograph assemblies has been progressed further
and design of the system from pick-up mirror to slicer has been started.
The mechanical
workshop has continued to fabricate components for the NIRI duplication.
Modifications have been made to the design of the OIWFS optable to accommodate
the changes necessary for NIFS and to the design of the cryocooler interfaces,
as suggested by Jeff Douglass to improve cooling performance and reduce
vibration.
The NIRI control
system drawings obtained from IfA were used to compile a parts list for
procurement and quotes have been obtained for the majority of components.
A recent version of
the NIRI Components Controller software has been installed and is being
modified to reflect the different NIFS mechanisms. The Detector controller IOC
has been assembled and the detector controller software design has seen some
progress.
The design of the
detector mounting board has been started and the stability of the SDSU
controller is being assessed.
With the RSC detector
contract having been executed on 12 October, science detector delivery is
assumed to take place 558 days after this date, or on 23 April 2002. Our plan
includes three months characterization at UH, time for transport to RSAA and
another six weeks verification before integration in NIFS at the start of the
fifth cooldown cycle. This pushes the date for transportation of NIFS to Hawaii
out to end of December 2002.
It has been agreed to
delay the CDR to 22 February 2001. The NIFS delivery date is being driven by
the science detector delivery.
No tasks were formally completed during the reporting period.
|
Task WBS |
hrs |
Finish Date |
Title |
Deliverables |
|
|
|
|
|
|
2.1.1
NIFS Critical
Design - Project Management
A continuing task. JvH: 46.5 hrs.
2.1.6
PS Miscellaneous
A continuing task to record various activities.
PJM: 13 hrs.
2.2.1
Revise OCDD
No progress this period.
2.2.2
Revise FPRD
Started, JvH: 5 hrs.
2.2.3
Science Case
No progress this period.
2.3.1
Requirements
Analysis
No progress this period.
2.4.6
Revise Error
Budget and Specify Tolerances
JH: 7 hrs.
2.4.12
Revise Nominal
Specifications
In conjunction with next task.
2.4.13
Determine
Temperature Compensated Specifications
JH: 87 hrs
2.4.16
Specify and
Negotiate IFU Machining
JH: 11 hrs.
2.5.2.3
Disperser Turret
Design
Continued: LP 80 hrs.
2.5.2.4
Develop IFU
No progress this period.
2.5.2.6
Design Array and
TriFold Mirror
PC: 15 hrs.
2.5.2.7
Detector Mount
Design
Thermal design: PC: 47 hrs, MDD: 14 hrs.
2.5.2.10
Design Entrance
Turret
Assembly design for entrance turret. PC: 38 hrs
2.5.2.12
Camera Mount
Design
JH: 7 hrs.
2.5.2.13
Design Baffle
System
No progress this period.
2.7.4
Component
Controller Software
MJ: 94.75 hrs.
PJY: 32.5 hrs.
4.1.1
Cryostat and
OIWFS Duplication – Project Management
A continuing task. JvH: 7 hrs.
4.2.1
Cryostat and
OIWFS Duplication – Design and Supervision
A continuing task. GJ: 108 hrs.
4.2.2 Cryostat and OIWFS
Duplication – Parts Fabrication
Workshop
effort 528 hrs this period.
4.3.1
Control system –
Design and Supervision
Prepare purchasing list and request quotes.
MID: 31.75 hrs.
5.8.7.1
Test Cryostat
Temperature Control – Design Control system
MDD: 22 hrs.
No documents were issued during the reporting period:
|
Document ID |
Rev |
Date |
Title |
|
|
|
|
|
The current schedule
is the schedule included in the “NIFS Revised Costing”. A schedule revised for
the expected delivery dates of the detectors and the late start on cryostat and
OIWFS duplication has been developed. It also takes into account the proposed
delayed CDR. This revised schedule was submitted during September. Further changes
will have to be made for the actual detector delivery dates and the effects of
delayed orders for long leadtime items resulting from the NIFS contract
uncertainty.
17 people have
contributed to the NIFS project during this period. They worked a total of 1276
hours, bringing the total for the project to 3959 hrs, which represents
approximately 13.0% of the total number of hours in the current project plan.
Listed below are the milestones defined in the NIFS contract. No
milestones were due during the reporting period.
|
Event |
Date |
Status |
|
(1)Contract fully signed |
August 2000 |
pending |
|
(2) Placement of order for vacuum
jacket forging |
August 2000 |
completed |
|
(3) AURA approval of Final FPRD
and OCDD |
5 December 2000 |
|
|
(4) AURA approval of Detailed
Design Documentation after CDR |
January 2001 |
|
|
(5) Start of first Cryostat and
OIWFS cooldown |
14 May 2001 |
|
|
(6) Completion of Cryostat and
OIWFS Duplication (As task is described in Conceptual Design Documentation) |
4 October 2001 |
|
|
(7) Completion of Spectrograph
Construction (As task is described in Conceptual Design Documentation) |
22 March 2002 |
|
|
(8) Authorization to ship
instrument given by AURA |
19 July 2002 |
|
|
(9) Completion of all Work and
Final Acceptance given by AURA |
1 October 2002 |
|
The exchange rate used
is the rate applicable to a particular transaction, or the rate on the last day
of the reporting period. On 29 September 2000 the rate was 0.535.
No income was gained
during the reporting period.
The NIFS account was
charged for 1263 hrs of work from 4 to 29 September 2000. This is the total
number of hours (1276) minus the hours for the Project Scientist (13). The
total charge is US$44,205 (A$82,626)
The following
expenditure was incurred during the reporting period.
4.2.2
Cryostat and
OIWFS Duplication – Fabrication – Aluminium, part of orders
O’Brien Aluminium US$ 7,718 A$14,426
4.6
Cryostat and
OIWFS Duplication – Consumables
Sockets, bolts US$ 30 A$
57
-------------- ------------
total US$ 7,748 A$14,483
The ANU accounting
system also includes ‘commitments’, where a purchase order has been raised, but
goods or services have not yet been delivered, invoiced and paid. New commitments
are listed here, but not included in the financial status report.
The order for a Lakeshore temperature controller and associated items
was authorised on 30 August before purchasing for NIFS was stopped, but was not
entered in the ANU financial system till 6 September.
4.3.2 Control
system – General Fabrication – Science detector temperature controller
Lakeshore US$ 7,257 A$13,565
|
Date |
Description |
Income (US$) |
Income (A$) |
Outgoings (US$) |
Outgoings (A$) |
|
29 Jul 00 |
Labour |
|
|
37,940 |
64,524 |
|
01 Sep 00 |
Labour |
|
|
48,125 |
83,696 |
|
01 Sep 00 |
Other Costs |
|
|
1,607 |
2,773 |
|
29 Sep 00 |
Labour |
|
|
44,205 |
82,626 |
|
29 Sep 00 |
Other Costs |
|
|
7,748 |
14,483 |
|
29 Sep 00 |
Balance |
|
|
139,625 |
248,102 |
The only technical
problem impeding project progress is the unavailability of some as-built
information on NIRI and its control software.
The purchase and
delivery of items on the critical path of the project may be delayed because of
RSAA hesitation to commit to large external purchases without the backing of a
contract.
RSAA will continue to
provide labour for the NIFS project, but will make no further large external
commitments. Ordering of the OIWFS optable machining, the OIWFS lenses, the
SDSU controllers and parts for the control system are on hold. Possible
measures to circumvent this problem are being explored.
The following Action Items are outstanding.
|
No. |
Action |
Who |
Status |
Due Date |
|
1 |
ICD16
Parameter Definition Format. Clarification |
RAN |
NIRI information being sought. |
|
|
2 |
Revise
NIFS schedule to reflect FPA delivery lead time |
JvH |
Closed Plan updated |
|
|
3 |
Generate
ordered list of "As Built" NIRI drawings |
JvH |
Closed List provided |
|
|
4 |
Negotiate
delivery schedule for As Built NIRI drawings with IfA |
RAN |
|
|
|
5 |
Determine
status of NIRI manuals |
RAN |
|
|
|
6 |
Determine
specifications and manufacturer of NIRI CaF2 window |
RAN |
Closed Information provided |
|
|
7 |
Make
tar archive of operational NIRI software |
RAN |
Closed |
|
|
8 |
Determine
status of IfA OIWFS fabrication |
RAN |
|
|
|
9 |
Send 7
cryo stepper motors to ANU |
RAN |
|
|
|
10 |
A
flip-in acquisition mirror will be incorporated into the design |
JvH |
Closed. Documentation to be changed
as required |
|
|
11 |
Send examples of Commisioning and Verification Plans |
RAN |
|
|
|
12 |
Relay urgency of NIFS contract approval |
RAN |
|
|
|
13 |
Check impact of late OIWSF parts delivery by UH on NIFS schedule |
JvH |
Closed. Early May 2001 is latest
delivery possible on the currently proposed plan. |
|