|
|
AUSTRALIAN NATIONAL UNIVERSITY Monthly
Report 14 Created: 15 May 2001 Last modified: 17 May 2001 |
MONTHLY REPORT FOR MARCH/APRIL 2001
Jan van Harmelen
Research
School of Astronomy and Astrophysics
Institute
of Advanced Studies
Australian
National University
Revision
History
|
Revision No. |
Author & Date |
Approval & Date |
Description |
|
Revision 1 |
Jan van Harmelen 15 May 2001 |
Peter McGregor 18 May 2001 |
Original document. |
|
|
|
|
|
Contents
This period, most effort has been concentrated
on coordinating the preparation for the Critical Design Review, and then on the
CDR itself.
The CDR, on 19 and 20 April, was successful.
The Committee’s report has been received and our response has been returned to
Gemini.
This report on NIFS
activities covers the eight-week period from 5 March to 27 April 2001.
As the CDR can be seen
as the ultimate progress report, no monthly report was generated for March.
This report catches up on the work and expenditure for the two month period,
but has little to add to the CDR information.
The search for
competent mechanical design and electronics technical staff continues. The
positions will be advertised again late in May.
The latest information
on the NIFS progress was presented at the CDR, only one week before the end of
this reporting period.
We are continuing work
towards vacuum testing of the cryostat starting 29 May, and the start of the
first cooldown on 3 July.
The design of
modifications to our test dewar has started.
Design detailing and
the production of fabrication drawings of the spectrograph is about to start.
Work is continuing on
developing our own schematics and PCB layouts for most of the control system,
and a good start has been made on the construction of the control system with
mechanical assembly of the electronics crates advancing.
A revised schedule has
been submitted as part of the CDR documentation. This will be considered as the
“current schedule”.
All Critical Design
Study tasks have been closed at the end of the reporting period. Any work still
outstanding will be carried out as part of the spectrograph construction.
|
Task WBS |
hrs |
Finish Date |
Title |
Deliverables |
|
2.1.1 |
487 |
27 Apr 2001 |
Project Management |
N/A |
|
2.1.6 |
135 |
27 Apr 2001 |
PS miscellaneous |
N/A |
|
2.2.3 |
258 |
27 Apr 2001 |
Science Case |
CDR Docs |
|
2.3.2 |
11 |
27 Apr 2001 |
Acceptance Test Plan |
CDR Docs |
|
2.3.8 |
2690 |
27 Apr 2001 |
Produce CDR Documentation |
CDR Docs |
|
2.6.2.2 |
192 |
27 Apr 2001 |
Detector Board PCB Layout |
PCB Layout |
|
2.6.2.3 |
28 |
27 Apr 2001 |
Flex Circuit Wiring Design |
Schematics |
|
2.6.2.4 |
38 |
27 Apr 2001 |
Flex Circuit PCB Layout |
PCB Layout |
|
3 |
284 |
27 Apr 2001 |
CDR |
N/A |
4.1.1
Cryostat and
OIWFS Duplication – Project Management
A continuing task. JvH: 4 hrs.
4.2.1
Cryostat and
OIWFS Duplication – Design and Supervision
A continuing task. CV and others: 38 hrs.
4.2.2 Cryostat and OIWFS
Duplication – Parts Fabrication
Workshop
effort 447 hrs this period.
4.3.1
Control System –
Design and Supervision
Purchasing and design. MID: 28 hrs.
4.3.2
Control System –
General Fabrication
Equipment mounting: JA: 116 hrs.
Apart from the CDR documentation, no documents
were issued during the reporting period.
|
Document ID |
Rev |
Date |
Title |
|
|
|
|
|
The current schedule
is the schedule included in the CDR Documentation.
18 people have
contributed to the NIFS project during this period. They worked a total of 1515
hours, bringing the total for the project to 13,555 hrs, which represents
approximately 43.4% of the total number of hours in the current project plan.
The number of hours allocated for the critical design study has been overspent
by 7.2%.
Listed below are the milestones defined in the NIFS contract. Milestone
3, AURA approval of Final OCDD and FPRD has been postponed to the CDR date,
which is now set for 19-20 April 2001.
|
Event |
Date |
Status |
|
(1)Contract fully signed |
August 2000 |
Completed |
|
(2) Placement of order for vacuum
jacket forging |
August 2000 |
Completed |
|
(3) AURA approval of Final FPRD
and OCDD |
5 December 2000 |
To be submitted with CDR
documentation |
|
(4) AURA approval of Detailed
Design Documentation after CDR |
January 2001 |
CDR 19 April 2001 |
|
(5) Start of first Cryostat and
OIWFS cooldown |
14 May 2001 |
|
|
(6) Completion of Cryostat and
OIWFS Duplication (As task is described in Conceptual Design Documentation) |
4 October 2001 |
|
|
(7) Completion of Spectrograph
Construction (As task is described in Conceptual Design Documentation) |
22 March 2002 |
|
|
(8) Authorization to ship
instrument given by AURA |
19 July 2002 |
|
|
(9) Completion of all Work and
Final Acceptance given by AURA |
1 October 2002 |
|
The exchange rate used
is the rate applicable to a particular transaction, or the rate on the last day
of the reporting period. On 27 April 2001 the rate was 0.505.
No income was gained
during the reporting period.
The NIFS account was
charged for 1361hrs of work for the reporting period. This is the total number
of hours (1514) minus the hours for the Project Scientist (153). The total
charge is US$57,635 (A$114,129)
The following table
lists all expenditure incurred and all new commitments made during the
reporting period.
Note: “Type” indicates: e – expenditure, c - commitment

Measures are in place
to minimise delays resulting from the unavailability of as-built and
performance information on NIRI and its control software.
The next minor
milestones on the current schedule are the start of cryostat vacuum tests on 29
May and the start of cooldown cycle 0 (cryostat with Cold Work Surface and
radiation shields) on 3 July. The cooldown start depends on the timely delivery
of the cryocoolers and their mounting bellows from the manufacturers. In case
of delays with the coolers, we may have to take up Gemini’s offer to lend us
spare coolers. The delivery of helium hoses, fittings, and differential
pressure switches by Gemini is also on the critical path.
There are no financial
problems.
The following Action Items are outstanding.
|
No. |
Action |
Who |
Status |
|
4 |
Negotiate
delivery schedule for As Built NIRI drawings with IfA |
RAN |
Mechanical drawings received. |
|
9 |
Send 7
cryo stepper motors to ANU |
RAN |
1 received (no further action required till later) |