AUSTRALIAN NATIONAL UNIVERSITY

 

Monthly Report 14

 

Created: 15 May 2001

Last modified: 17 May 2001

 

---

 

MONTHLY REPORT FOR MARCH/APRIL 2001

 

Jan van Harmelen

 

Research School of Astronomy and Astrophysics

Institute of Advanced Studies

Australian National University

 

Revision History

 

Revision No.

Author &

Date

Approval &

Date

Description

Revision 1

Jan van Harmelen

15 May 2001

Peter McGregor

18 May 2001

Original document.

 

 

 

 

 

 

Contents

 

1     Project Scientist’s Report 2

2     Project Manager’s Report 2

3     Technical Progress. 2

4     Schedule Progress. 3

5     Financial Progress. 4

6     Problem Areas. 6

7     Action Items. 6


 

1           Project Scientist’s Report

 

This period, most effort has been concentrated on coordinating the preparation for the Critical Design Review, and then on the CDR itself.

 

The CDR, on 19 and 20 April, was successful. The Committee’s report has been received and our response has been returned to Gemini.

 

2            Project Manager’s Report

 

This report on NIFS activities covers the eight-week period from 5 March to 27 April 2001.

 

As the CDR can be seen as the ultimate progress report, no monthly report was generated for March. This report catches up on the work and expenditure for the two month period, but has little to add to the CDR information.

 

2.1         Staffing

The search for competent mechanical design and electronics technical staff continues. The positions will be advertised again late in May.

 

2.2         Progress

The latest information on the NIFS progress was presented at the CDR, only one week before the end of this reporting period.

 

We are continuing work towards vacuum testing of the cryostat starting 29 May, and the start of the first cooldown on 3 July.

 

The design of modifications to our test dewar has started.

 

Design detailing and the production of fabrication drawings of the spectrograph is about to start.

 

Work is continuing on developing our own schematics and PCB layouts for most of the control system, and a good start has been made on the construction of the control system with mechanical assembly of the electronics crates advancing.

 

2.3         Schedule

A revised schedule has been submitted as part of the CDR documentation. This will be considered as the “current schedule”.

 

 

3           Technical Progress

 

3.1         Completed Tasks

All Critical Design Study tasks have been closed at the end of the reporting period. Any work still outstanding will be carried out as part of the spectrograph construction.

 

Task WBS

hrs

Finish Date

Title

Deliverables

2.1.1

487

27 Apr 2001

Project Management

N/A

2.1.6

135

27 Apr 2001

PS miscellaneous

N/A

2.2.3

258

27 Apr 2001

Science Case

CDR Docs

2.3.2

11

27 Apr 2001

Acceptance Test Plan

CDR Docs

2.3.8

2690

27 Apr 2001

Produce CDR Documentation

CDR Docs

2.6.2.2

192

27 Apr 2001

Detector Board PCB Layout

PCB Layout

2.6.2.3

28

27 Apr 2001

Flex Circuit Wiring Design

Schematics

2.6.2.4

38

27 Apr 2001

Flex Circuit PCB Layout

PCB Layout

3

284

27 Apr 2001

CDR

N/A

 

3.2         Tasks in Progress

4.1.1            Cryostat and OIWFS Duplication – Project Management

A continuing task. JvH: 4 hrs.

4.2.1            Cryostat and OIWFS Duplication – Design and Supervision

A continuing task. CV and others: 38 hrs.

4.2.2        Cryostat and OIWFS Duplication – Parts Fabrication

                Workshop effort 447 hrs this period.

4.3.1            Control System – Design and Supervision

Purchasing and design. MID: 28 hrs.

4.3.2            Control System – General Fabrication

Equipment mounting: JA: 116 hrs.

 

3.3         Documents Issued

Apart from the CDR documentation, no documents were issued during the reporting period.

 

Document ID

Rev

Date

Title

 

 

 

 

 

 

4           Schedule Progress

 

4.1         Updated Schedule

The current schedule is the schedule included in the CDR Documentation.

 

4.2         Project Statistics

18 people have contributed to the NIFS project during this period. They worked a total of 1515 hours, bringing the total for the project to 13,555 hrs, which represents approximately 43.4% of the total number of hours in the current project plan. The number of hours allocated for the critical design study has been overspent by 7.2%.

 

4.3         Milestones

Listed below are the milestones defined in the NIFS contract. Milestone 3, AURA approval of Final OCDD and FPRD has been postponed to the CDR date, which is now set for 19-20 April 2001.

 

Event

Date

Status

(1)Contract fully signed

August 2000

Completed

(2) Placement of order for vacuum jacket forging

August 2000

Completed

(3) AURA approval of Final FPRD and OCDD

5 December 2000

To be submitted with CDR documentation

(4) AURA approval of Detailed Design Documentation after CDR

January 2001

CDR 19 April 2001

(5) Start of first Cryostat and OIWFS cooldown

14 May 2001

 

(6) Completion of Cryostat and OIWFS Duplication (As task is described in Conceptual Design Documentation)

4 October 2001

 

(7) Completion of Spectrograph Construction (As task is described in Conceptual Design Documentation)

22 March 2002

 

(8) Authorization to ship instrument given by AURA

19 July 2002

 

(9) Completion of all Work and Final Acceptance given by AURA

1 October 2002

 

 

 

5           Financial Progress

 

The exchange rate used is the rate applicable to a particular transaction, or the rate on the last day of the reporting period. On 27 April 2001 the rate was 0.505.

 

5.1         Income

No income was gained during the reporting period.

 

5.2         Outgoings

5.2.1        Labour

The NIFS account was charged for 1361hrs of work for the reporting period. This is the total number of hours (1514) minus the hours for the Project Scientist (153). The total charge is US$57,635 (A$114,129)

 

5.2.2        Other Costs  - Expenditure and Commitments

 

The following table lists all expenditure incurred and all new commitments made during the reporting period.

 

Note: “Type” indicates: e – expenditure, c - commitment

 

5.3         Financial Status

 

 

6           Problem Areas

 

6.1         Technical Problems

Measures are in place to minimise delays resulting from the unavailability of as-built and performance information on NIRI and its control software.

 

6.2         Scheduling Problems

The next minor milestones on the current schedule are the start of cryostat vacuum tests on 29 May and the start of cooldown cycle 0 (cryostat with Cold Work Surface and radiation shields) on 3 July. The cooldown start depends on the timely delivery of the cryocoolers and their mounting bellows from the manufacturers. In case of delays with the coolers, we may have to take up Gemini’s offer to lend us spare coolers. The delivery of helium hoses, fittings, and differential pressure switches by Gemini is also on the critical path.

 

6.3         Financial Problems

There are no financial problems.

 

7           Action Items

 

The following Action Items are outstanding.

 

No.

Action

Who

Status

4

Negotiate delivery schedule for As Built NIRI drawings with IfA

RAN

Mechanical drawings received.

9

Send 7 cryo stepper motors to ANU

RAN

1 received (no further action required till later)